Willemen Bouw was established on 30 April 2025 through the merger of Willemen Construct, Cosimco, Franki Construct and Tools.

High pressure Hydrotreater Esso...
    
         This project was part of a worldwide effort...

Knooppunt A12 Londerzeel-Zuid -...
    
         Ten zuiden van Londerzeel kruist de A12 de...
Waste incineration plant Indaver-Suez - Doel
Description 
    The project concerns the construction of the new waste incinerator that recuperates energy from the incineration of waste.
The complex consists of an unloading hall, a concrete waste bunker, a furnace building, a turbine building, various concrete ash bunkers and a building for the scrubber.
The concrete bunkers are 40 m high and were constructed using a slipform.
Various 40 m high steel structures were also installed to accommodate the different parts of the production process.
The capacity of the fluidised bed furnace is 430 000 tonnes/year. This makes it one of the largest on the European continent.
location 
    Project Details
                        Contractor                    
                    
                Haven 1940, Molenweg, Doel, Oost-Vlaanderen, Belgium
                     
                    Client 
    Lurgi
      Engineering Office 
    Arcade
       
                    








 
                                       