Waste incineration plant Indaver-Suez - Doel
Description
The project concerns the construction of the new waste incinerator that recuperates energy from the incineration of waste.
The complex consists of an unloading hall, a concrete waste bunker, a furnace building, a turbine building, various concrete ash bunkers and a building for the scrubber.
The concrete bunkers are 40 m high and were constructed using a slipform.
Various 40 m high steel structures were also installed to accommodate the different parts of the production process.
The capacity of the fluidised bed furnace is 430 000 tonnes/year. This makes it one of the largest on the European continent.
location
Project Details
Contractor
Haven 1940, Molenweg, Doel, Oost-Vlaanderen, Belgium
Client
Lurgi
Engineering Office
Arcade