Data centre campus CyrusOne - Amsterdam (The Netherlands)
Description 
    Realisation of the closed shell of the new campus for US data centre operator CyrusOne with a capacity of 72 megawatts. The structure consists of 3,500 tonnes of steel and 4,000 m³ of concrete and is founded on 3,500 foundation piles.
Â
News
27/11/2019 - 10:15
  18/06/2019 - 12:00
  19/03/2019 - 16:30
  location 
    Project Details
                        Contractor                    
                    
                Polanenpark, Haarlem, Noord Holland, Netherlands
                     
                    Client 
    CyrusOne
      Architects 
    Hyphen
         Knevel Architecten
      Engineering Office 
    Pinnacle
      Surface area above ground 
    27 000m²
      Special features
                    
                  Construction period
 9 months
Start work
12-2018
End of work
09-2019
                    