Willemen Construct came into being on 1 July 2018 as a result of the merger between Willemen General Contractor and the construction department of Kumpen.
![](https://willemen.be/sites/default/files/styles/prev_next_nav_80x60/public/Willemen%20-%20St-Truiden%20Gazo%20-005-8141.jpg?itok=v6OAZ5qG)
GAZO - Sint-Truiden
GAZO is the redevelopment of the Gazometer...
![](https://willemen.be/sites/default/files/styles/prev_next_nav_80x60/public/2017-03-23%20Scholen%20van%20Morgen%20-%20Borsbeek%20-%20Werffoto%20%281%29.jpg?itok=CN2DLt_T)
Schools of Tomorrow - Borsbeek
The Gesubsidieerde Vrije Basisschool and the...
Training centre IFAPME - Tournai
Description
Construction of a training centre with a surface area of 7,850 m².
Â
News
19/12/2017 - 08:45
07/06/2017 - 08:30
location
Project Details
Contractor
Terrain Paul Pastur , Doornik , Hainaut, Belgium
Client
IFAPME
Surface area above ground
7 850m²
Special features
Construction period
2 years 2 months
Start work
02-2016
End of work
04-2018