NMBS Railway station - Roeselare

Description 

Franki Construct began the renovation of Roeselare station on 6 January 2016. A part of the station will be demolished and replaced by new buildings, another part will be dismantled and renovated. A broader and pleasantly lit passage under the railway viaduct, and a more spacious and car-free station square will turn the area into an attractive focal point for living and working, travelling and shopping.

The station will remain in service while the work is being carried out; therefore the work will be divided into two parts. First, the new building on the right-hand side of the station will be completed, then the renovation of the existing station hall and the office building will commence. The main bearing structure of this part of the station building will be preserved, allowing the new ceiling to be attached to it. Along platform 3, at the rear of the station, a new, overhanging section will be added.

The offices on the first floor will be improved, and the fire compartmentalisation will be carried out in consultation with the fire department. A new high-voltage substation, the sprinkler system and the smoke extraction installation will be renewed as well. The total ground surface area is 4,200 square metres. A 2,500 square meter waterproof ceiling will be placed under the existing railway bridge. Also, a new roof will be mounted over the tracks and the station.

Since 1998 Franki Construct has been part of Willemen Groep, the largest family construction group in Belgium.

 
location 

Project Details

Contractor
Stationsplein , Roeselaere, West-Vlaanderen, Belgium
Client 
Infrabel
Architects 
Eurostation
Edward Sorgeloose Architecture
Engineering Office 
Eurostation
Surface area above ground 
4 200m²
Surface area subterranean 
2 500m²
Construction period
2 years
Start work
01-2016
End of work
01-2018