Since 1998 Franki has been part of Willemen Groep, the largest family construction group in Belgium.

Guldendal - Malines
With 29 family homes and 39 flats, Guldendal...

R9 (southern part) - Charleroi
Public works contract for the complete...
Ecole de l'Ouest - Lodelinsart
Description
Demolition and reconstruction of the 'Ecole de l'Ouest' in Lodelinsart. We installled temporary modules during the works.
The works took a year and a half to complete. The building comprises 5 kindergarten classrooms, 6 primary school classrooms, a courtyard, play areas, a sports hall and a janitorial service. The total surface of the building is 1,325 m² for a total volume of 9,275 m³. The surrounds were also part of our assignment.
News
21/12/2016 - 10:00
location
Project Details
Contractor
rue Alfred Georges, 156, Lodelinsart, Hainaut, Belgium
Client
Ville de Charleroi
Price
€3.600.000
Architects
IGRETEC
Engineering Office
Igretec
Construction period
2 years 3 months
Start work
09-2014
End of work
12-2016