Bridge over Moerbrugsestraat - Oostkamp
Description
The project involves replacing the arch bridge over Moerbrugsestraat in Oostkamp, widening the bridge over the River Brook and adapting the Moerbrugsestraat road alignment between Rivierstraat and Stationsstraat. The new arch bridge consists of two lanes for motorised traffic and a cycle path along both sides.
- Foundation, sub- and superstructure of the bridge;
- Adjustment of cross-section and longitudinal profile;
- Local adaptation of overhead lines and signalling.
location
Project Details
Contractor
Moerbrugsestraat , Oostkamp, West-Vlaanderen, Belgium
Client
Infrabel
Engineering Office
Tuc Rail
Construction period
1 year 7 months
Start work
11-2016
End of work
06-2018