Willemen Construct came into being on 1 July 2018 as a result of the merger between Willemen General Contractor and the construction department of Kumpen.
![](https://willemen.be/sites/default/files/styles/prev_next_nav_80x60/public/Willemen%20-%20St-Truiden%20Gazo%20-005-8141.jpg?itok=v6OAZ5qG)
GAZO - Sint-Truiden
GAZO is the redevelopment of the Gazometer...
![](https://willemen.be/sites/default/files/styles/prev_next_nav_80x60/public/HuisVDSolidariteit_nov2020_002LR.jpg?itok=nBbznLhn)
Huis van de Solidariteit - Brussels
Complete renovation of an office building in...
The Link - Berchem
Description
Structural construction of two energy-efficient office buildings with a total surface of 27,000 m².
Â
News
31/05/2017 - 17:30
location
Project Details
Contractor
Posthofbrug 1-2, Berchem, Antwerpen, Belgium
Client
Girenwa
Price
€12.600.000
Architects
ABV+ Architecten
Surface area above ground
27 000m²
Construction period
1 year 6 months
Start work
09-2016
End of work
03-2018