Construction of a signalling centre for the Belgian railways and demolition of an existing post office building.The complete building forms a Faraday cage to protect the railway signalling.This was accomplished by earthing 4,100 m² of concrete walls and interconnecting all concrete reinforcement. - Foundation: 134 screw piles
- Earthworks: 3,000 m³
- Structure: Reinforced concrete: 2,510 m³ concrete and 215 tonnes of rebar
- Sectional steel: 50 tonnes
- External wall cladding: 620 m² aluminium panels, 2,000 m² stone panels, 155 m² glass curtain walling.
- Heating + Cooling: air critical premises by heating with convectors
- climate control boxes with air reversal on heat
- ventilation of premises with high-voltage air groups
- control via PRBA's
- lightning protection of structures and people
- lightning protection of electrical and electronic systems
- ICT equipment (data cabinets, cabling, fire alarm cables + + access control and security in fallow)
- lighting, control by KNX KNX DAL / gateways
- power supply through assured power: power over infrabel power distribution and power over the public grid via separate routes
- electric lift
|