Project Details


Activities
Civil Engineering
Bridges
Railway infrastructure & stations

Contractors
Franki Construct

location
Bergensesteenweg 1261
1070 Anderlecht
Belgium
Brussels BE

Client
Infrabel

End User
NMBS

Engineering Office
TUC Rail

Construction period 
3 years 3 months

Start work 
04-2011

End of work 
07-2014


 
  • Construction railway bed for line L50B, along both sides of line L50.
  • Length: 4 km
  • Widening of 3 existing railway bridges
  • Renovation of 5 overpasses over the railway lines
  • New train station
  • Supporting walls and green terraces/retaining walls
  • Construction of covered trench: lg: 200m/acoustic buffer
  • Green terraces.
Franki Construct

Kartuizersweg 1
2550 Kontich (Belgium)
tel +32 3 821 16 80
FCVINFO@franki.be
www.franki.be

Since 1998 Franki Construct has been part of Willemen Groep, the largest family construction group in Belgium.