PROJECT PDF
 
 
 
Willemen Groep
Boerenkrijgstraat 133, BE - 2800 Mechelen
tel +32 15 569 965, groep@willemen.be
 
Railway infrastructure works - Anderlecht
 

Project Details


Activities
Civil Engineering
Bridges
Railway infrastructure & stations

Contractors
Willemen Construct

location
Bergensesteenweg 1261
1070 Anderlecht
Belgium
Brussels BE

Client
Infrabel

End User
NMBS

Engineering Office
TUC Rail

Construction period 
3 years 3 months

Start work 
04-2011

End of work 
07-2014


 
  • Construction railway bed for line L50B, along both sides of line L50.
  • Length: 4 km
  • Widening of 3 existing railway bridges
  • Renovation of 5 overpasses over the railway lines
  • New train station
  • Supporting walls and green terraces/retaining walls
  • Construction of covered trench: lg: 200m/acoustic buffer
  • Green terraces.
Willemen Construct

Boerenkrijgstraat 133
2800 Mechelen, Antwerpen (Belgium)
tel +32 15 56 99 65
bouw@willemen.be
www.willemen.be

Willemen Construct came into being on 1 July 2018 as a result of the merger between Willemen General Contractor and the construction department of Kumpen.